Question 17 of 100
Free Preview · 100 of 333 · questions 1–100 of 333 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Risk thresholds establish clear criteria for when escalation is required. When a risk is identified that exceeds the defined threshold (in this case, >2 weeks schedule impact), the PM must escalate according to the governance structure. Waiting for the risk to occur defeats the purpose of proactive risk management, and manipulating estimates to avoid escalation violates professional ethics and undermines risk governance.