Question 13 of 100
Free Preview · 100 of 333 · questions 1–100 of 333 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Risk appetite can vary by risk category. A low risk appetite for safety means the organization wants rigorous controls and conservative approaches for safety risks. A high risk appetite for innovation means the organization is willing to accept more uncertainty when pursuing innovative solutions. This guides the PM in selecting appropriate response strategies — aggressive mitigation for safety, acceptance or moderate mitigation for innovation. Risk appetite directly informs project risk decisions.