Question 4 of 78
Free Preview · 78 of 258 · questions 1–78 of 258 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Stakeholders with high influence and high interest should be managed closely. These are typically key players who can significantly impact project success and are deeply engaged. The power/interest grid categorizes stakeholders into four groups: Manage Closely (high power, high interest), Keep Satisfied (high power, low interest), Keep Informed (low power, high interest), and Monitor (low power, low interest).