Question 31 of 34
Free Preview · 34 of 113 · questions 1–34 of 113 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Schedule compression involves shortening the project duration without reducing scope. Two primary techniques are crashing (adding resources such as overtime, additional crews, or premium shipping to shorten critical path activities — increases cost) and fast-tracking (performing activities in parallel that would normally be sequential — increases risk). In construction, both must be carefully evaluated for cost impacts, safety implications, and quality risks.