Question 24 of 34
Free Preview · 34 of 113 · questions 1–34 of 113 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Float (or slack) is the amount of time an activity can be delayed without affecting the project completion date (total float) or without delaying the start of successor activities (free float). Activities on the critical path have zero total float. Understanding float is essential for construction schedulers because it identifies flexibility in the schedule, helps with resource allocation, and determines which activities require the closest monitoring.