Question 12 of 34
Free Preview · 34 of 113 · questions 1–34 of 113 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Construction cost estimates progress through levels of accuracy as design detail increases: conceptual/order of magnitude (-50%/+100%), schematic/budget (-30%/+50%), design development (-15%/+20%), and definitive/detailed (-5%/+10%). Understanding these levels is crucial for construction managers because decisions and commitments should match the available level of estimate accuracy. Presenting preliminary estimates as definitive creates unrealistic expectations.