Question 48 of 204
Free Preview · 204 of 677 · questions 1–204 of 677 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
D happens before looking for a maintenance window. Plan/test/rollback → choose maintenance window → notify customers → implement change. Therfor answer is C.
Once the maintenance window is determined, the next operational step is to send maintenance window notifications so customers have advance notice of disruptions/outages.
C. Notify customers. - Rollback plan was developed before the selecting the maintenance window. Notify customers should occur next.