Question 37 of 204
Free Preview · 204 of 677 · questions 1–204 of 677 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Because the change is already approved and the PM has updated the project plan/end date, the next step in the change control cycle is to communicate the approved change and its implementation details to affected stakeholders so execution aligns with the updated baseline/plan. THEN you implement changes. Answer is B
Tricky question. Don't let the approval throw you off. The last step that happened was "update the project plan", after that is implement. D
Wrong. Implement the change. Look up change control process.