Question 31 of 204
Free Preview · 204 of 677 · questions 1–204 of 677 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
c review existing artifacts
The correct answer is: C. Review existing artifacts ✅ Explanation: When a project manager is new to a project and needs to understand the purpose of the project during the planning phase, the best step is to review existing artifacts such as: Project charter Business case Requirements documentation Previous project documentation These documents provide important background and context about the project's goals, scope, and rationale.
Project artifacts are essentially the important documents of the Project. He would review these to get a grasp on what is going on.