Question 24 of 204
Free Preview · 204 of 677 · questions 1–204 of 677 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The correct answer is: A. Time and materials contract ✅ Explanation: The scenario describes work where: The duration is uncertain. The cost cannot be calculated in advance. A third party is performing the work. It’s a short-term task. In such cases, a Time and Materials (T&M) contract is most appropriate because: It allows the buyer to pay for actual time spent (e.g., hourly/daily rate) and materials used. It offers flexibility when scope or duration is not well-defined.
Time & Materials makes the most sense. Since both time & materials are both unknowns, doing a fixed price contract or a cost-plus agreement doesn't make much sense. SOW and MSA aren't contract types, they outline the work.
The answer is A. Time and materials contract. A time and materials contract is a type of contract where the contractor is paid for the time they spend working on the project and the materials they use. This type of contract is often used for short-term projects where the duration and cost cannot be accurately estimated in advance. The other options are not as suitable.