Question 47 of 156
Free Preview · 156 of 517 · questions 1–156 of 517 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The program manager should analyze the newly discovered dependency, assess its impact on the program, update the program management plan, and actively coordinate between the affected projects. Managing cross-project dependencies is a core program management responsibility. Exam tip: Managing interdependencies between components is one of the primary reasons programs exist—always address them at the program level.