Question 11 of 65
Free Preview · 65 of 216 · questions 1–65 of 216 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The portfolio governance board provides oversight and strategic direction for the portfolio. It makes key decisions about component selection, prioritization, authorization, and termination. It does not manage day-to-day project activities, which is the responsibility of project and program managers.