Question 8 of 190
Free Preview · 190 of 631 · questions 1–190 of 631 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Cost and staffing levels are typically highest during the Executing phase because this is when the majority of the project work is being performed. Team members are actively building deliverables, resources are being consumed at the highest rate, and the project budget is being spent most rapidly. During Initiating and Planning, the team is smaller and costs are lower. During Closing, resources are released and spending decreases as remaining work winds down.