Question 6 of 190
Free Preview · 190 of 631 · questions 1–190 of 631 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The Initiating phase is where the project is formally authorized through the project charter and key stakeholders are identified in the stakeholder register. The project charter defines the project at a high level, names the project manager, and gives them authority to apply organizational resources. The stakeholder register documents information about identified stakeholders. These are foundational documents that must exist before detailed planning can begin.