Question 24 of 190
Free Preview · 190 of 631 · questions 1–190 of 631 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The five process groups follow a logical sequence: Initiating (authorize the project), Planning (define approach and baselines), Executing (perform the work), Monitoring & Controlling (track and adjust), and Closing (formalize acceptance and close out). While Monitoring & Controlling overlaps with all other groups, this sequence represents the general flow. Note that these are process groups, not phases - a project can have multiple phases, and each phase may go through all five process groups.