- Progressive elaboration is the iterative process of increasing the level of detail in a project management plan as greater amounts of information and more accurate estimates become available. It is a characteristic of projects that distinguishes them from operations. Rolling wave planning is a specific planning technique where near-term work is planned in detail while future work is planned at a higher level. Iterative development is a methodology approach, and scope creep refers to uncontrolled expansion of project scope.